MathematicsTime & WorkPPSCID: PPP-3793
A washerman irons 4 shirts in 12 minutes. How many shirts can he iron in one hour?
A16
B20 ✓ Correct answer
C24
D30
✓ Correct answer: 20
Full explanation
If 4 shirts take 12 minutes, then 1 shirt takes 3 minutes. In 60 minutes (1 hour), he can iron 60/3 = 20 shirts. The correct answer is 20.
MathematicsTime & WorkCSSID: CPP-471
A herd of cows consumes the available food in 150 days. If the number of cows is reduced by 10, the food lasts for 160 days. How many cows were there originally?
A150
B160 ✓ Correct answer
C100
DNone of these
✓ Correct answer: 160
Full explanation
The correct answer is 160. Let n = original cows. Total food = 150n. With (n-10) cows for 160 days: 160(n-10) = 150n → 10n = 1600 → n = 160.
MathematicsTime & WorkCSSID: CPP-501
200 trees in 30 days (group 1). After removing 20 workers, 200 trees in 40 days. Original group size?
A60
B70
C80 ✓ Correct answer
DNone of these
✓ Correct answer: 80
Full explanation
The correct answer is 80. Work=workers x days. 30n=40(n-20) → 10n=800 → n=80.
MathematicsTime & WorkCSSID: CPP-526
16 men+12 women complete work in 20 days. 18 women complete same work in 40 days. Days for 12 men+27 women?
A16 ✓ Correct answer
B18
C21
DNone of these
✓ Correct answer: 16
Full explanation
The correct answer is 16. One woman's work per day=1/(18x40)=1/720. From the first equation, one man's work per day=1/480. 12 men+27 women complete 1/40+3/80=5/80=1/16 of the work per day, so the job takes 16 days.
MathematicsTime & WorkFPSCID: FPP-1570
If 8 men can build a wall in 12 days, how many days will 6 men take?
A14 days
B15 days
C16 days ✓ Correct answer
D18 days
✓ Correct answer: 16 days
Full explanation
The work needs 96 man-days, so 6 men take 16 days.
MathematicsTime & WorkFPSCID: FPP-1721
If 5 workers complete a job in 10 days, how long will 10 workers take?
A5 days ✓ Correct answer
B10 days
C20 days
D15 days
✓ Correct answer: 5 days
Full explanation
Doubling the workers halves the time, so 10 workers take 5 days.
MathematicsTime & WorkFPSCID: FPP-2352
How many minutes are there in 2.5 hours?
A120
B130
C150 ✓ Correct answer
D180
✓ Correct answer: 150
Full explanation
There are 150 minutes in 2.5 hours, since 2.5 x 60 = 150.
MathematicsTime & WorkFPSCID: FPP-2801
A student can solve "q "questions in 1/h hour. At this rate how many questions can she solve in q hours?
Ahq
B1/hq
CNone of these
Dq²h ✓ Correct answer
✓ Correct answer: q²h
Full explanation
She solves q questions in 1/h hour, so her rate is qh questions per hour, and in q hours she solves q²h questions.
MathematicsTime & WorkFPSCID: FPP-2913
36 men can complete a piece of work in 18 days. In how many days will 27 men complete the same work?
A22
B24 ✓ Correct answer
C26
DNone of these
✓ Correct answer: 24
Full explanation
24. 36 men take 18 days, so the work is 648 man-days, and 648 divided by 27 men is 24 days.
MathematicsTime & WorkFPSCID: FPP-3712
If 20 men can construct n wall in 5 days, then 10 men can construct the same wall in _______ days.
A5
B20
C10 ✓ Correct answer
Dnone
✓ Correct answer: 10
Full explanation
10. If 20 men take 5 days, 10 men take twice as long, which is 10 days.
MathematicsTime & WorkFPSCID: FPP-4318
15 masons can build the wall in 20 days. How many masons will build the wall in 12 days?
A15 days
B12 days
C23 days
DNone ✓ Correct answer
✓ Correct answer: None
Full explanation
The work needs 15 × 20 = 300 mason-days, so in 12 days it needs 300 / 12 = 25 masons, which is not among the options, so the answer is None.
MathematicsTime & WorkFPSCID: FPP-4727
A worker can finish a job in 12 days, and another worker can finish the same job in 18 days. Working together, in how many days will they finish the job?
A7.2 days ✓ Correct answer
B6 days
C8 days
D9 days
✓ Correct answer: 7.2 days
Full explanation
Together they finish 1/12 + 1/18 = 5/36 of the job per day, so they take 36/5 = 7.2 days, so 7.2 days is the correct answer.
MathematicsTime & WorkNADRAID: FPP-8516
A worker can finish a job in 12 days. How much of the job does he finish in 3 days?
AOne quarter ✓ Correct answer
BOne third
COne half
DOne sixth
✓ Correct answer: One quarter
Full explanation
One quarter. In 3 days out of 12, the worker finishes one quarter of the job.
MathematicsTime & WorkNADRAID: FPP-8531
If 8 workers build a wall in 15 days, how many days would 10 workers take at the same rate?
A14 days
B16 days
C10 days
D12 days ✓ Correct answer
✓ Correct answer: 12 days
Full explanation
12 days. The work is 8 times 15, or 120 worker-days, and 120 divided by 10 is 12 days.
MathematicsTime & WorkFPSCID: FPP-10389
A can do a piece of work in 8 days and B can do it in 24 days. In how many days can they finish it together?
A32
B16
C8
D6 ✓ Correct answer
✓ Correct answer: 6
Full explanation
6. Together they finish 1/8 + 1/24 = 32/192 of the work per day, so they take 192/32 = 6 days.
MathematicsTime & WorkFPSCID: FPP-10738
A can do a piece of work in 20 days and B can do it in 30 days. In how many days can they finish it together?
A25
B20
C12 ✓ Correct answer
D50
✓ Correct answer: 12
Full explanation
12. Together they finish 1/20 + 1/30 = 50/600 of the work per day, so they take 600/50 = 12 days.
MathematicsTime & WorkFPSCID: FPP-10873
If 1 worker can finish a job in 12 days, how long will 3 workers take working at the same rate?
A4 days ✓ Correct answer
B12 days
C24 days
D15 days
✓ Correct answer: 4 days
Full explanation
4 days. Three workers working together take 12 ÷ 3 = 4 days.
MathematicsTime & WorkFPSCID: FPP-10879
A can do a piece of work in 10 days and B can do it in 15 days. In how many days can they finish it together?
A12
B10
C6 ✓ Correct answer
D25
✓ Correct answer: 6
Full explanation
6. Together they finish 1/10 + 1/15 = 25/150 of the work per day, so they take 150/25 = 6 days.
MathematicsTime & WorkFPSCID: FPP-10908
A can do a piece of work in 12 days and B can do it in 18 days. In how many days can they finish it together?
A15
B12
C36/5 ✓ Correct answer
D30
✓ Correct answer: 36/5
Full explanation
36/5. Together they finish 1/12 + 1/18 = 30/216 of the work per day, so they take 216/30 = 36/5 days.
MathematicsTime & WorkFPSCID: FPP-11437
If 5 workers complete a job in 12 days, 1 worker would take:
A60 days ✓ Correct answer
B7 days
C24 days
D17 days
✓ Correct answer: 60 days
Full explanation
1 worker would take 60 days to complete the job alone.