IntelligenceTime & WorkPPSCFPSCNTSID: QR-291
9 workers finish a job in 8 days. How many days will 6 workers take to do the same job?
A10 days
B12 days ✓ Correct answer
C14 days
D16 days
✓ Correct answer: 12 days
Full explanation
The correct answer is 12 days. The job takes 9 x 8 = 72 worker-days, so 6 workers take 72 / 6 = 12 days. Why the others are wrong: 10 days — 6 x 10 = 60 worker-days, which is less than the job needs. 14 days — 6 x 14 = 84 worker-days, which is more than the job needs. 16 days — 6 x 16 = 96 worker-days, which is more than the job needs.
IntelligenceTime & WorkPPSCFPSCNTSID: QR-304
A can finish a task in 12 days and B can finish the same task in 36 days. How many days will they take to finish the task working together?
A7 days
B9 days ✓ Correct answer
C8 days
D10 days
✓ Correct answer: 9 days
Full explanation
Together they do 1/12 + 1/36 = 1/9 of the task in one day, so they finish it in 9 days. Why the others are wrong: 7 days — that would need them to do 1/7 of the task each day, which is more than they do. 8 days — that would need them to do 1/8 of the task each day, which is more than they do. 10 days — that would need them to do 1/10 of the task each day, which is less than they do.
IntelligenceTime & WorkPPSCFPSCNTSID: QR-317
A can finish a task in 8 days and B can finish the same task in 8 days. How many days will they take working together?
A2 days
B6 days
C4 days ✓ Correct answer
D8 days
✓ Correct answer: 4 days
Full explanation
The correct answer is 4 days. A does 1/8 of the task in a day and B does 1/8, so together they do 1/8 + 1/8, which is 1/4 of the task in a day, and the task takes 4 days. Why the others are wrong: 2 days — in 2 days they would do 2/4 of the task, not the whole task. 6 days — in 6 days they would do 6/4 of the task, which is more than the whole task. 8 days — 8 days is how long each of them takes alone, but working together they are faster.