Tap an option to check your answer — the correct answer and full explanation appear after you choose.
IntelligenceTime & WorkPPSCFPSCNTSID: NWC-031
12 men can do a job in 8 days. How many days will 16 men take to do the same job?
A5 days
B6 days ✓ Correct answer
C7 days
D9 days
✓ Correct answer: 6 days
Full explanation
16 men will take 6 days. The job needs 12 x 8 = 96 man-days, and 96 / 16 = 6 days. Why the others are wrong: 5 days — 16 men in 5 days give only 80 man-days, not 96. 7 days — 16 men in 7 days give 112 man-days, more than the 96 needed. 9 days — more men must take fewer days than 8, not more.
IntelligenceTime & WorkPPSCFPSCNTSID: QR-031
A can finish a task in 10 days and B can finish the same task in 15 days. How many days will they take working together?
A5 days
B12 days
C7 days
D6 days ✓ Correct answer
✓ Correct answer: 6 days
Full explanation
6 days. Together they finish 1/10 + 1/15 = 1/6 of the task each day, so the whole task takes 6 days. Why the others are wrong: 5 days — that would need a combined rate of 1/5 per day. 7 days — that would need a combined rate of 1/7 per day. 12 days — that is close to B's time alone, but together they are faster than either one alone.
IntelligenceTime & WorkPPSCFPSCNTSID: QR-044
5 men can do a job in 12 days. How many days will 10 men take to do the same job?
A10 days
B12 days
C6 days ✓ Correct answer
D24 days
✓ Correct answer: 6 days
Full explanation
5 men × 12 days = 60 man-days, so 10 men take 60 ÷ 10 = 6 days. Why the others are wrong: 10 days — that would be the time for 6 men, not 10 men. 12 days — that is the time for 5 men, not 10 men. 24 days — more men take fewer days, not more.
IntelligenceTime & WorkPPSCFPSCNTSID: QR-057
A can finish a task in 9 days and B can finish the same task in 18 days. How many days will they take working together?
A4 days
B5 days
C6 days ✓ Correct answer
D9 days
✓ Correct answer: 6 days
Full explanation
Together they finish 1/9 + 1/18 = 1/6 of the task per day, so they take 6 days. Why the others are wrong: 4 days — in 4 days they would finish only 4/6 of the task. 5 days — in 5 days they would finish only 5/6 of the task. 9 days — that is the time A takes alone, not the time they take together.
IntelligenceTime & WorkPPSCFPSCNTSID: QR-070
10 men can do a job in 6 days. How many days will 15 men take to do the same job?
A3 days
B4 days ✓ Correct answer
C5 days
D9 days
✓ Correct answer: 4 days
Full explanation
4 days. The job takes 60 man-days, and 60 divided by 15 is 4 days. Why the others are wrong: 3 days - 3 days would need 20 men, not 15 men. 5 days - 5 days would need 12 men, not 15 men. 9 days - 9 days would need fewer men, not more men.
IntelligenceTime & WorkPPSCFPSCNTSID: QR-083
A can finish a task in 20 days and B can finish the same task in 30 days. How many days will they take working together?
A10 days.
B12 days. ✓ Correct answer
C15 days.
D25 days.
✓ Correct answer: 12 days.
Full explanation
Together they do 1/20 + 1/30 = 1/12 of the task in one day, so they take 12 days. Why the others are wrong: 10 days. — 10 days would mean they do 1/10 of the task each day, which is more than 1/20 + 1/30.. 15 days. — 15 days would mean they do 1/15 of the task each day, which is less than 1/20 + 1/30.. 25 days. — 25 days is the average of 20 and 30, not the time they take together..
IntelligenceTime & WorkPPSCFPSCNTSID: QR-096
A can finish a task in 16 days and B can finish the same task in 16 days. How many days will they take working together?
A6 days.
B7 days.
C8 days. ✓ Correct answer
D9 days.
✓ Correct answer: 8 days.
Full explanation
The correct answer is 8 days. Together they finish 1/16 + 1/16 = 2/16 = 1/8 of the task in one day, so they take 8 days to finish the whole task. Why the others are wrong: 6 days. - in 6 days they would finish only 6/8 of the task, not the whole task. 7 days. - in 7 days they would finish only 7/8 of the task, not the whole task. 9 days. - they finish the task in 8 days, so 9 days is one day too many.
IntelligenceTime & WorkPPSCFPSCNTSID: QR-109
A can finish a task in 12 days and B can finish the same task in 4 days. How many days will they take working together?
A3 days. ✓ Correct answer
B8 days.
C6 days.
D16 days.
✓ Correct answer: 3 days.
Full explanation
Together they finish 1/12 plus 1/4 of the task each day, which is 1/3 of the task per day, so they finish it in 3 days. Why the others are wrong: 8 days. — 8 days is neither one's time alone nor their combined time. 6 days. — 6 days does not match the combined rate of 1/3 of the task per day. 16 days. — 16 days is the sum of their separate times, not their time together.
IntelligenceTime & WorkPPSCFPSCNTSID: QR-122
6 men can do a job in 10 days. How many days will 12 men take to do the same job?
A5 days. ✓ Correct answer
B3 days.
C10 days.
D20 days.
✓ Correct answer: 5 days.
Full explanation
5 days. doubling the men halves the time, so 12 men take 10 / 2 = 5 days. Why the others are wrong: 3 days. — 3 days would need 20 men at the same rate. 10 days. — 10 days is the time for 6 men, not 12. 20 days. — 20 days is the time for 3 men, not 12.
IntelligenceTime & WorkPPSCFPSCNTSID: QR-135
20 men can do a job in 9 days. How many days will 12 men take to do the same job?
A15 days ✓ Correct answer
B12 days
C10 days
D18 days
✓ Correct answer: 15 days
Full explanation
The correct answer is 15 days. The job needs 20 x 9 = 180 man-days, and 180 divided by 12 = 15 days. Why the others are wrong: 12 days — 12 days would need 15 men, not 12. 10 days — 10 days would need 18 men, not 12. 18 days — 18 days would need 10 men, not 12.
IntelligenceTime & WorkPPSCFPSCNTSID: QR-148
A can finish a task in 8 days and B can finish the same task in 24 days. How many days will they take working together?
A6 days ✓ Correct answer
B4 days
C5 days
D7 days
✓ Correct answer: 6 days
Full explanation
The correct answer is 6 days. 6 days is the time they take together, because 1/8 + 1/24 = 4/24 = 1/6 of the task per day. Why the others are wrong: 4 days — 4 days is wrong because their combined daily work is 1/6 of the task, not 1/4.. 5 days — 5 days is wrong because their combined daily work is 1/6 of the task, not 1/5.. 7 days — 7 days is wrong because their combined daily work is 1/6 of the task, not 1/7..
IntelligenceTime & WorkPPSCFPSCNTSID: QR-161
15 men can do a job in 4 days. How many days will 10 men take to do the same job?
A4 days
B5 days
C6 days ✓ Correct answer
D8 days
✓ Correct answer: 6 days
Full explanation
The correct answer is 6 days. The job takes 15 times 4, or 60 man-days, so 10 men take 60 divided by 10, which is 6 days. Why the others are wrong: 4 days — 4 days is the time for 15 men, and fewer men take longer, not the same time. 5 days — 5 days does not follow from 60 man-days divided by 10 men. 8 days — 8 days does not follow from 60 man-days divided by 10 men.
IntelligenceTime & WorkPPSCFPSCNTSID: QR-174
9 men can do a job in 12 days. How many days will 18 men take to do the same job?
A9 days
B12 days
C4 days
D6 days ✓ Correct answer
✓ Correct answer: 6 days
Full explanation
The work is 9 men multiplied by 12 days, which is 108 man-days, so 18 men take 108 divided by 18, which is 6 days. Why the others are wrong: 9 days — doubling the men halves the time from 12 days to 6 days, not 9. 12 days — 12 days is the time 9 men take, not 18 men. 4 days — 18 men take 108 divided by 18, which is 6 days, not 4.
IntelligenceTime & WorkPPSCFPSCNTSID: QR-200
A can finish a task in 10 days and B can finish the same task in 10 days. How many days will they take working together?
A3 days
B4 days
C5 days ✓ Correct answer
D10 days
✓ Correct answer: 5 days
Full explanation
5 days. A and B will take 5 days working together, because A does 1/10 and B does 1/10 of the task per day, so together they do 1/5 of the task per day. Why the others are wrong: 3 days — it does not match 1/10 + 1/10. 4 days — it does not match 1/10 + 1/10. 10 days — that is the time one person alone needs, not two working together.
IntelligenceTime & WorkPPSCFPSCNTSID: QR-213
10 men can do a job in 12 days. How many days will 15 men take to do the same job?
A6 days
B10 days
C18 days
D8 days ✓ Correct answer
✓ Correct answer: 8 days
Full explanation
The correct answer is 8 days. The job takes 10 x 12, or 120 man-days, and 120 divided by 15 men is 8 days. Why the others are wrong: 6 days — 6 days would need 20 men, not 15 men. 10 days — 10 days would need 12 men, not 15 men. 18 days — 18 days is more days than 12, but more men must take fewer days.
IntelligenceTime & WorkPPSCFPSCNTSID: QR-226
A can finish a task in 5 days and B can finish the same task in 20 days. How many days will they take working together?
A3 days
B4 days ✓ Correct answer
C5 days
D6 days
✓ Correct answer: 4 days
Full explanation
Together they will take 4 days. In one day A does 1/5 of the task and B does 1/20, so together they do 1/4 of the task each day. Why the others are wrong: 3 days — that would mean they do one third of the task each day, which is more than 1/5 + 1/20. 5 days — that is the time A alone takes, so working together must take less time. 6 days — that is more than the time A alone takes, so it cannot be the time they take together.
IntelligenceTime & WorkPPSCFPSCNTSID: QR-239
Two workers can each finish a job alone in 8 days. How many days will they take if they work together?
A2 days
B4 days ✓ Correct answer
C8 days
D16 days
✓ Correct answer: 4 days
Full explanation
The answer is 4 days. Each worker finishes 1/8 of the job in a day, so together they finish 1/8 + 1/8 = 1/4 of the job in a day, and the whole job takes 4 days. Why the others are wrong: 2 days — two workers at this rate finish one fourth of the job each day, not one half. 8 days — this is the time one worker takes alone, not both together. 16 days — adding the two times together gives a longer time, not a shorter one.
IntelligenceTime & WorkPPSCFPSCNTSID: QR-252
A can finish a task in 8 days and B can finish the same task in 12 days. How many days will they take working together?
A4 days.
B6 days.
C5 days.
D4.8 days. ✓ Correct answer
✓ Correct answer: 4.8 days.
Full explanation
4.8 days. Together they do 1/8 + 1/12 = 5/24 of the task in one day, so they take 24/5 = 4.8 days. Why the others are wrong: 4 days. — that is less than the correct time. 5 days. — that is a little more than the correct time. 6 days. — that is more than the correct time.
IntelligenceTime & WorkPPSCFPSCNTSID: QR-265
8 workers can build a wall in 6 days. How many days will 4 workers take to build the same wall?
A3 days.
B6 days.
C24 days.
D12 days. ✓ Correct answer
✓ Correct answer: 12 days.
Full explanation
12 days. 12 days. is the answer, because halving the workers doubles the time: 6 days times 2 is 12 days. Why the others are wrong: 3 days. — 3 days. would need twice as many workers, not half as many.. 6 days. — 6 days. is the time for 8 workers, and 4 workers will take longer.. 24 days. — 24 days. would need only 2 workers, not 4 workers..
IntelligenceTime & WorkPPSCFPSCNTSID: QR-278
A is twice as efficient as B. If B alone can do a job in 12 days, in how many days can A and B together do it?
A3 days
B4 days ✓ Correct answer
C6 days
D8 days
✓ Correct answer: 4 days
Full explanation
The correct answer is 4 days. A is twice as efficient as B, so A alone can do the job in half of 12 days, which is 6 days. Together they do 1/6 plus 1/12 of the job in a day, which is 1/4 of the job, so the whole job takes 4 days. Why the others are wrong: 3 days — together they would do 1/3 of the job a day, which is more than the 1/4 they actually do. 6 days — that is the time A alone would take, not A and B together. 8 days — together they would do only 1/8 of the job a day, which is less than the 1/4 they actually do.