12 men can do a job in 8 days. How many days will 16 men take to do the same job?

  1. A5 days
  2. B6 days ✓ Correct answer
  3. C7 days
  4. D9 days
IntelligenceTime & Work PPSC FPSC NTSID: QR-031

A can finish a task in 10 days and B can finish the same task in 15 days. How many days will they take working together?

  1. A5 days
  2. B12 days
  3. C7 days
  4. D6 days ✓ Correct answer
IntelligenceTime & Work PPSC FPSC NTSID: QR-044

5 men can do a job in 12 days. How many days will 10 men take to do the same job?

  1. A10 days
  2. B12 days
  3. C6 days ✓ Correct answer
  4. D24 days
IntelligenceTime & Work PPSC FPSC NTSID: QR-057

A can finish a task in 9 days and B can finish the same task in 18 days. How many days will they take working together?

  1. A4 days
  2. B5 days
  3. C6 days ✓ Correct answer
  4. D9 days
IntelligenceTime & Work PPSC FPSC NTSID: QR-070

10 men can do a job in 6 days. How many days will 15 men take to do the same job?

  1. A3 days
  2. B4 days ✓ Correct answer
  3. C5 days
  4. D9 days
IntelligenceTime & Work PPSC FPSC NTSID: QR-083

A can finish a task in 20 days and B can finish the same task in 30 days. How many days will they take working together?

  1. A10 days.
  2. B12 days. ✓ Correct answer
  3. C15 days.
  4. D25 days.
IntelligenceTime & Work PPSC FPSC NTSID: QR-096

A can finish a task in 16 days and B can finish the same task in 16 days. How many days will they take working together?

  1. A6 days.
  2. B7 days.
  3. C8 days. ✓ Correct answer
  4. D9 days.
IntelligenceTime & Work PPSC FPSC NTSID: QR-109

A can finish a task in 12 days and B can finish the same task in 4 days. How many days will they take working together?

  1. A3 days. ✓ Correct answer
  2. B8 days.
  3. C6 days.
  4. D16 days.
IntelligenceTime & Work PPSC FPSC NTSID: QR-122

6 men can do a job in 10 days. How many days will 12 men take to do the same job?

  1. A5 days. ✓ Correct answer
  2. B3 days.
  3. C10 days.
  4. D20 days.
IntelligenceTime & Work PPSC FPSC NTSID: QR-135

20 men can do a job in 9 days. How many days will 12 men take to do the same job?

  1. A15 days ✓ Correct answer
  2. B12 days
  3. C10 days
  4. D18 days
IntelligenceTime & Work PPSC FPSC NTSID: QR-148

A can finish a task in 8 days and B can finish the same task in 24 days. How many days will they take working together?

  1. A6 days ✓ Correct answer
  2. B4 days
  3. C5 days
  4. D7 days
IntelligenceTime & Work PPSC FPSC NTSID: QR-161

15 men can do a job in 4 days. How many days will 10 men take to do the same job?

  1. A4 days
  2. B5 days
  3. C6 days ✓ Correct answer
  4. D8 days
IntelligenceTime & Work PPSC FPSC NTSID: QR-174

9 men can do a job in 12 days. How many days will 18 men take to do the same job?

  1. A9 days
  2. B12 days
  3. C4 days
  4. D6 days ✓ Correct answer
IntelligenceTime & Work PPSC FPSC NTSID: QR-200

A can finish a task in 10 days and B can finish the same task in 10 days. How many days will they take working together?

  1. A3 days
  2. B4 days
  3. C5 days ✓ Correct answer
  4. D10 days
IntelligenceTime & Work PPSC FPSC NTSID: QR-213

10 men can do a job in 12 days. How many days will 15 men take to do the same job?

  1. A6 days
  2. B10 days
  3. C18 days
  4. D8 days ✓ Correct answer
IntelligenceTime & Work PPSC FPSC NTSID: QR-226

A can finish a task in 5 days and B can finish the same task in 20 days. How many days will they take working together?

  1. A3 days
  2. B4 days ✓ Correct answer
  3. C5 days
  4. D6 days
IntelligenceTime & Work PPSC FPSC NTSID: QR-239

Two workers can each finish a job alone in 8 days. How many days will they take if they work together?

  1. A2 days
  2. B4 days ✓ Correct answer
  3. C8 days
  4. D16 days
IntelligenceTime & Work PPSC FPSC NTSID: QR-252

A can finish a task in 8 days and B can finish the same task in 12 days. How many days will they take working together?

  1. A4 days.
  2. B6 days.
  3. C5 days.
  4. D4.8 days. ✓ Correct answer
IntelligenceTime & Work PPSC FPSC NTSID: QR-265

8 workers can build a wall in 6 days. How many days will 4 workers take to build the same wall?

  1. A3 days.
  2. B6 days.
  3. C24 days.
  4. D12 days. ✓ Correct answer
IntelligenceTime & Work PPSC FPSC NTSID: QR-278

A is twice as efficient as B. If B alone can do a job in 12 days, in how many days can A and B together do it?

  1. A3 days
  2. B4 days ✓ Correct answer
  3. C6 days
  4. D8 days