Structural Engineering MCQs

20 practice MCQs on this page Page 11 of 18

Tap an option to check your answer — the correct answer and full explanation appear after you choose.

Civil EngineeringStructural Engineering BPSCID: BPP-3519

In reinforced concrete, steel is mainly provided to resist:

  1. ACompression
  2. BTension ✓ Correct answer
  3. CShear only
  4. DTorsion only
Civil EngineeringStructural Engineering BPSCID: BPP-3520

The minimum number of longitudinal bars in a rectangular reinforced concrete column is:

  1. A2
  2. B3
  3. C4 ✓ Correct answer
  4. D6
Civil EngineeringStructural Engineering BPSCID: BPP-3521

The slump test is used to measure the:

  1. AStrength of concrete
  2. BWorkability of concrete ✓ Correct answer
  3. CDensity of concrete
  4. DSetting time of cement
Civil EngineeringStructural Engineering BPSCID: BPP-3522

What is the characteristic compressive strength of M20 grade concrete?

  1. A10 MPa
  2. B15 MPa
  3. C20 MPa ✓ Correct answer
  4. D25 MPa
Civil EngineeringStructural Engineering BPSCID: BPP-3523

Which of the following is the main binding material in concrete?

  1. ASand
  2. BAggregate
  3. CCement ✓ Correct answer
  4. DWater
Civil EngineeringStructural Engineering BPSCID: BPP-3524

The initial setting time of ordinary Portland cement should not be less than:

  1. A15 minutes
  2. B30 minutes ✓ Correct answer
  3. C45 minutes
  4. D60 minutes
Civil EngineeringStructural Engineering BPSCID: BPP-3526

Which type of footing is provided when two columns are close to each other?

  1. AIsolated footing
  2. BCombined footing ✓ Correct answer
  3. CRaft footing
  4. DStrip footing
Civil EngineeringStructural Engineering BPSCID: BPP-3527

The ratio of water to cement in concrete mainly affects its:

  1. AColour
  2. BStrength and workability ✓ Correct answer
  3. CWeight only
  4. DSetting time only
Civil EngineeringStructural Engineering BPSCID: BPP-3528

A slab is called a one-way slab when the ratio of longer span to shorter span is:

  1. ALess than 2
  2. BGreater than 2 ✓ Correct answer
  3. CEqual to 1
  4. DLess than 1
Civil EngineeringStructural Engineering BPSCID: BPP-3529

Stirrups in a reinforced concrete beam are provided to resist:

  1. ABending moment
  2. BShear force ✓ Correct answer
  3. CTorsion only
  4. DAxial load
Civil EngineeringStructural Engineering BPSCID: BPP-3530

The curing of concrete is done to:

  1. AIncrease its colour
  2. BKeep it moist for proper hydration ✓ Correct answer
  3. CReduce its weight
  4. DSpeed up setting only
Civil EngineeringStructural Engineering BPSCID: BPP-3531

Which aggregate size is considered coarse aggregate?

  1. ALess than 4.75 mm
  2. BGreater than 4.75 mm ✓ Correct answer
  3. CLess than 2 mm
  4. DGreater than 20 mm only
Civil EngineeringStructural Engineering BPSCID: BPP-3532

The effective span of a simply supported beam is taken as:

  1. AClear span only
  2. BCentre-to-centre distance between supports ✓ Correct answer
  3. CSpan plus depth
  4. DTwice the clear span
Civil EngineeringStructural Engineering BPSCID: BPP-3533

Which of the following loads is a live load on a building?

  1. ASelf-weight of the slab
  2. BWeight of furniture and people ✓ Correct answer
  3. CWeight of walls
  4. DWeight of the foundation
Civil EngineeringStructural Engineering BPSCID: BPP-3954

A beam that is fixed at one end and free at the other is called a:

  1. ACantilever beam ✓ Correct answer
  2. BSimply supported beam
  3. CContinuous beam
  4. DFixed beam
Civil EngineeringStructural Engineering BPSCID: BPP-3535

Prestressed concrete is used mainly to:

  1. AReduce the size of members
  2. BOvercome the low tensile strength of concrete ✓ Correct answer
  3. CIncrease workability
  4. DReduce setting time
Civil EngineeringStructural Engineering BPSCID: BPP-3536

The maximum bending moment in a cantilever beam carrying a uniformly distributed load over its full length occurs at:

  1. AThe free end
  2. BThe fixed end ✓ Correct answer
  3. CThe mid-span
  4. DThe point of maximum shear
Civil EngineeringStructural Engineering BPSCID: BPP-3537

What is the unit of measurement of concrete in estimation?

  1. ASquare metre
  2. BCubic metre ✓ Correct answer
  3. CRunning metre
  4. DKilogram
Civil EngineeringStructural Engineering BPSCID: BPP-3538

Which of the following is a doubly reinforced beam?

  1. ABeam with steel in tension zone only
  2. BBeam with steel in both tension and compression zones ✓ Correct answer
  3. CBeam without steel
  4. DBeam with stirrups only
Civil EngineeringStructural Engineering BPSCID: BPP-3640

In a simply supported beam, the maximum bending moment under a central point load occurs at which point?

  1. AAt midspan ✓ Correct answer
  2. BAt the supports
  3. CAt one-third of the span
  4. DAt the free end

Practice these MCQs interactively